How Long Does a Kitchen Remodel Take? Typically Four to Six Weeks
Back to Blog
Tips & Advice

How Long Does a Kitchen Remodel Take? Typically Four to Six Weeks

Sam HubbardFounder, Renovus Custom InteriorsApril 20269 min read

Updated November 13, 2026

How long does a kitchen remodel take? Construction is typically four to six weeks. The full range is two to fourteen weeks, depending on the project.

Before construction starts, we finish the design, work out lead times, and order the cabinets and appliances during preconstruction. We set your start date around those lead times, so once work begins, something moves the job along every day.

If you are planning a kitchen in Tryon, Landrum, Columbus, Saluda, or Lake Lure, here is how the timeline works, from the first call to the day you cook in your new kitchen.

The short version

  • Construction: typically four to six weeks. The full range is two to fourteen weeks, depending on the project.
  • Before construction: design, lead times and ordering happen during preconstruction. Cabinets and appliances are ordered before your start date. Countertops are templated on site after the cabinets go in, so their fabrication time is part of construction.
  • Longest wait: usually the cabinets, and that wait comes before construction starts.
  • Before construction starts: a written week by week schedule, updated as decisions get made and lead times confirm.

The nine phases

The nine phases below describe a larger kitchen job. Phases 1 and 2 happen during preconstruction, before your start date. The construction weeks are phases 3 through 9, and a smaller project may skip some of these steps.

Phase 1: Design and selections

This is where a project sets itself up for a smoother build, or for trouble later.

We sit down with you and walk through every decision: cabinet line and door style, countertop material and edge profile, hardware, faucet, sink, lighting plan, electrical changes, appliance specs, flooring, backsplash, paint colors. Every choice gets locked in before we order anything.

A single late decision, say a hardware change three weeks in, can push your finish date by a week. Hardware and the faucet are ordered with everything else, and those holes get drilled when the pieces go in. Change either one late and you’re waiting on a reorder while the schedule flexes. Decisions made in design can save weeks on site.

Homeowner job during this phase: show up to selection meetings, make decisions, sign off on the final scope.

Phase 2: Ordering and lead times

Cabinetry is the long pole. Semi custom lines usually take about a month to six weeks from order to delivery. Full custom from a regional shop runs 6 to 10 weeks. We work those lead times out during preconstruction and order cabinets and appliances before the project begins. Your start date is set around them, so your kitchen isn’t opened up and then left waiting.

Countertops are different. They are templated on site after cabinets are installed, because they have to fit the actual cabinet positions, not the drawings. A stone shop we’ve used for years then cuts and finishes the slabs at the shop. That fabrication time is part of the construction weeks.

Other things have lead times too. Specialty appliances, especially Wolf, Sub Zero and paneled refrigerators, can run 6 to 12 weeks. Custom tile, specialty lighting and imported faucets can also stretch the schedule. We flag every long lead item up front and order it during preconstruction, so nothing surprises you.

Phase 3: Demo (2 to 5 days)

Day one feels productive. The old kitchen comes out fast. Cabinets, countertops, flooring, backsplash, sometimes drywall and ceiling lighting. Dumpster goes in the driveway, plastic sheeting goes up to keep dust out of the rest of the house.

Demo often uncovers something. Old plumbing in worse shape than expected, electrical that needs updating, subfloor damage. We document anything we find and walk through change orders with you before we do any more work.

Phase 4: Rough work

Plumbing rough in (moving supply lines and drains for new sinks or appliance locations), electrical rough in (new circuits, new outlets, under cabinet lighting wiring, recessed light cans), HVAC adjustments if needed, and any framing for layout changes.

Phase 5: Drywall, paint prep, and flooring (1 week)

Drywall patching where walls were opened or moved. Skim coat and sand. Prime. Flooring goes in next, before cabinets, for hardwood and LVP installations so the floor runs continuously under cabinet runs.

Phase 6: Cabinet install (3 to 7 days)

The kitchen starts to look like a kitchen. Boxes go in level (every one is shimmed and checked), then doors and drawers, then crown molding and toe kicks. A skilled installer can hang an average kitchen in 3 to 5 days. Custom kitchens with stacked uppers, specialty trim, and built ins take longer.

Phase 7: Countertop template, fab, and install

Once cabinets are set, a stone shop we’ve used for years templates the actual surfaces. They take that template back to the shop, cut the slabs, and polish the edges. On install day they bring the finished tops, set them, seam them, and seal them. Faucet holes get drilled when the faucet goes in.

The kitchen is out of use during this phase, with no sink, no countertop and no running water.

Phase 8: Backsplash, plumbing trim, electrical trim (1 week)

Tile or LVP backsplash goes up. The plumber connects the sink, faucet, dishwasher, and any other fixtures. The electrician installs the under cabinet lights, switches, outlets, and pendants. Range hood gets ducted and connected.

By the end of this week, your kitchen is functional. You can cook in it.

Phase 9: Punch list and final (3 to 5 days)

Touch up paint. Door and drawer adjustments. Hardware install. Final cleaning. The kitchen gets walked with you, and anything that isn’t right goes on a list: a misaligned cabinet door, a paint nick, a missing piece of trim. Everything on the list gets fixed before the final invoice.

What a foothills kitchen adds to the schedule

If your kitchen is in an older home in Tryon, Landrum, Columbus or Saluda, a few things can add time. Older houses can mean uneven floors, and patched plumbing or wiring that needs work once the walls are open. We can’t know what’s behind a wall until it’s open, so we leave room in the plan for them and talk through anything we find with you before it turns into a surprise. The longer story is in what we find when we open the walls.

That applies to a kitchen remodel timeline in Tryon, NC, a kitchen remodel in Landrum, SC, and a Polk County kitchen remodel in general. Read more about Tryon and Landrum, or see how we handle kitchen remodels.

Why projects run long

Three things can stretch a kitchen remodel timeline:

1. Late decisions. Changing the hardware finish three weeks in can cost a week. Switching cabinet door styles can cost a month. See kitchen decisions that cost the most to change later.

2. Long lead specialty items. A specialty range can take 12 weeks to arrive. We order these during preconstruction and set your start date around them, so the wait comes before your kitchen is opened up, not in the middle of the job.

3. Unforeseen conditions in older homes. Wiring or plumbing that needs attention once the walls are open, subfloor damage. We can’t prevent these, but we can document them and price them clearly. They can cause delays, but typically the job keeps moving.

How to keep yours on schedule

  • Make selections before construction starts. All of them.
  • Finish your selections during preconstruction, so long lead items can be ordered before your start date.
  • Don’t change scope mid project unless it’s worth the schedule cost.
  • Ask for a written week by week schedule before construction starts.
  • Pick a contractor who gives you one point of contact and one phone number for the whole job.

For the home side of the work, see how to prepare for a kitchen remodel. If you’re still choosing, read how to hire a kitchen remodeler and how to read a remodeling bid.

Does the size or level of the kitchen change the timeline?

It can. Kitchen size and the level you choose both change the schedule, mostly through how much has to be ordered, built and installed. We use the same three levels as the Tryon kitchen cost guide.

  • Low level: your existing cabinet boxes stay, so there’s less to order and less to tear out.
  • Typical level: new semi custom cabinets and an island, so cabinet lead time matters more, and more of the schedule sits in ordering.
  • High level: custom cabinets, a built in refrigerator, a commercial grade cooktop and hood, and a wall oven. These are long lead items that can set your start date.

More cabinets and more counter mean more to order, template and install, whatever the level. We don’t put a week count on each level, because lead times and what is in your walls change it from one house to the next.

If you’re planning a bathroom instead, it typically takes 3 to 6 weeks of construction. We cover it in how long a bathroom remodel takes.

Preconstruction agreement, Instant Estimate, and the written schedule

Our preconstruction agreement covers the design work that turns a ballpark into a buildable plan. It is also when we work out lead times, and cabinets and appliances are ordered before the project begins. The fee is on the pricing page.

Instant Estimate on the pricing page covers kitchens, baths, mudrooms and closets. It gives you a starting range for the room and level you pick. The detailed proposal from preconstruction is the real number, because the Instant Estimate cannot see hidden conditions.

You get a written week by week schedule before construction starts, and it updates as decisions get made and lead times confirm.

The first conversation is a free 30 minute consultation by phone, video call or on site. We talk through how you use the kitchen and flag cost drivers early. After that, Sam gives you a ballpark range. From there comes the preconstruction agreement, then a detailed proposal with a timeline and a decision list. Nothing is locked until you sign.

Cost context for the same kitchen levels

Here are the same three levels, priced on a kitchen of about 200 square feet with 30 linear feet of cabinets:

  • Low, about $29,500: existing cabinet boxes stay with new Shaker style fronts and hardware, a new range and refrigerator, laminate counters, a midpriced sink and faucet, resilient flooring and paint.
  • Typical, about $79,800: a new kitchen with about 30 linear feet of semi custom wood cabinets and a 3 by 5 foot island, laminate counters, a stainless double sink, a built in microwave, a dishwasher, a disposal and custom lighting.
  • High, about $161,100: custom cabinets with built in sliding shelves, marble or quartzite counters, a tile or glass backsplash, designer faucets, a built in refrigerator, a commercial grade cooktop and hood, a wall oven and undercabinet lighting.

A recent Tryon kitchen came in at $66,800. See the project and the fuller notes in kitchen remodel cost in Tryon, or the pricing page.

Frequently asked questions

How long does a kitchen remodel take? Construction is typically four to six weeks. The full range is two to fourteen weeks, depending on the project. Before that comes preconstruction, where we finish the design, work out lead times, and order the cabinets and appliances. We set your start date around those lead times, so once work starts, something moves the job along every day. Countertops are templated on site after the cabinets are in, so their fabrication time is part of the build schedule.

How long is my kitchen unusable? Your kitchen is out of use from demo until the backsplash and trim week, when the sink, appliances and lights get connected. Demo takes 2 to 5 days. Rough work and countertop install follow, and for part of that stretch you have no sink or counters. How long it lasts depends on your kitchen, and we don’t add the steps up, because every kitchen is different.

What takes the longest in a kitchen remodel? Cabinets are usually the longest wait, and specialty appliances can run longer still. Full custom cabinets from a regional shop run 6 to 10 weeks, and specialty appliances like Wolf, Sub Zero and paneled refrigerators can run 6 to 12 weeks. We work out those lead times during preconstruction and order these items before the project begins, so your start date is set around them.

Can a kitchen remodel be done faster? Sometimes a little, and decisions made early can save time. Make every selection during preconstruction, so long lead items can be ordered before your start date, and don’t change scope mid project unless it’s worth the schedule cost. A late hardware change can cost a week. We don’t promise speed, because lead times and what is behind your walls set much of the pace.

When should I start planning if I want it done by a certain date? Start early, because design and the ordering of cabinets and appliances happen during preconstruction, before your start date. Specialty appliances and full custom cabinets have the longest lead times, so they push the start date out further. Countertops are templated on site after the cabinets are in, so their fabrication time is part of the build schedule. Tell us your date on the first call, and we’ll talk through what it takes to plan toward it.

Does an older foothills home take longer? It can. Older homes in Tryon, Landrum, Columbus and Saluda sometimes have uneven floors, or patched plumbing and wiring that needs work once the walls are open. How much that adds depends on what the walls hold. Sometimes something stands out on a walkthrough, but a lot only shows once the walls are open. We talk through anything we find before it becomes a surprise. You can read more in what we find when we open the walls.

Next step

Sam brings 32 years of experience (since 1994) to every Renovus kitchen, and we’re glad to talk through yours. Call 864.806.2630 or reach out through our contact page.

Homeowner reviews are on our reviews page, rated 4.9 from 51 Google reviews.

Sam

Let's See If We're the Right Fit.

The first step is a free 30 minute consultation by phone, video call, or on site. We talk through what you're trying to solve and tell you honestly whether we're the right team for it.

Talk with us